K. Nelson, project manager of Print Software, Inc., wants you to prepare a project network; compute the early, late, and slack activity times; determine the planned project duration; and identify the critical path. His assistant has collected the following information for the Color Printer Drivers Software Project: ID Description Predecessor Time An External specifications None 8 B Review design features A Â Â 2 C Document new features A Â Â 3 D Write software A Â Â 60 E Program and test B Â Â 40 F Edit and publish notes C Â Â 2 G Review manual D Â Â 2 H Alpha site E, F 20 I Print manual G Â Â 10 J Beta site H, I 10 K Manufacture J 12 L Release and ship K Â Â 3