1-What is a Work Breakdown Structure (WBS) for a project? Explain various approaches for Developing WBSs.
2-Consider the following project network diagram:
The black circle before Task A means Start, after Task J means Finished. The number associated with Task name represents the duration of the task (e.g. I 4, means the duration of the task I is 4).
Based on the above diagram, answer the following questions:
- List all the paths in the above network along with respective lengths.
- Calculate (ES, EF, LS, LF) of the following tasks shown on the table below?
- Which tasks have Non-Zero flsoat time?
Task |
ES |
LS |
|
Task |
EF |
LF |
G |
A |
|||||
B |
C |
|||||
H |
J |
3-Not every project is a six Sigma project. What makes a project a potential Six Sigma
project?