The planning department of an electronics firm has set up the activities for developing and production of a new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a five-day workweek and the project starts on January 4, 2017. Activity Description Activity Activity Time ID Predecessor (weeks) 1 Staf None 2 2 Develop market program 1    3 3 Select channels of distribution 1    8 4 Patent 1 12 5 Pilot production 1 4 6 Test market 5 4 7 Ad promotion 2 4 8 Set up for production 4, 6 16 The project team has requested that you create a network for the project, and determine if the project can be completed in 45 weeks.

 

 