:Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table Period 1 2 3 4 5 6 7 8 9 10 11 12 Gross requirements 20 30 40 70 20 10 30 50 “Holding cost $3.50/unit/week, setup cost $150, load time I wook, beginning inventory 40 Develop a lot for lot solution (onter your responses as whole numbers) Period 1 2 3 4 tig 6 7 8 9 10 11 12 Gross requirements 20 30 40 7020 1080 50 Scheduled receipt Projected On hand 40 “Holding cost-$3.50/unit/week, setup cost $150, lead time=1 week beginning inventory = 40 Develop a lot for lot solution Center your responses as whole numbers) 1 2 4 8 11 3 30 5 40 6 7 70 20 10 1080 12 50 20 Penod Gross requirements Scheduled receipt Projected On hand Net Requirements Planned Order receipt Planned Order release 40 The total cost is
 