The following image displays the bill of material (BOM) for a toy manufacturing company.
Complete the following MRP records for Components for the Components B, C, E and F. All the information required is given in the above BOM and the below MRP records. (If needed the below tables can be easily copied and pasted to excel)
ITEM A Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements 15 20 10 10 10 20 10 10 Scheduled receipts 22 5 Projected On-hand Inventory: 33 Planned order Releases Q= 10,LT=2 , SS= 10 ITEM B Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements Scheduled receipts 5 Projected On-hand Inventory: 10 Planned order Releases Q= 5,LT=1 , SS= 10 ITEM C Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements Scheduled receipts 30 10 15 Projected On-hand Inventory: 20 Planned order Releases Q= LFL,LT=1 , SS= 10 ITEM D Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Gross requirements Scheduled receipts 5 Projected On-hand Inventory: 25 Planned order Releases Q= 25,LT=1 , SS= 25