A student has developed a project and wants to accelerate the
schedule
Present
Accelerated
Duration
Cost
Duration Cost
a
4 $100
2
$300
b
4 $ 50
3
$100
c
5 $250
4
$350
d
3 $100
cannot accelerate
e
7 $100
6
$170
f
7 $300
5
$600
. Below network diagram (Activity on Arrow) and table show all
information needed. Dotted arrow is used as a “dummyâ€; no activity,
only shows precedence. Partial crashing is available. Show your
work for crashing.
- Without any crashing (acceleration), how long is the
project expected to take? - Crash the project by maximum available time. What
activities should we crash? - What is the total additional cost for maximum
crash?