Given Covid, restaurants are under extreme pressure increase productivity. Below is the list of activities at Dunk’s Donut and Coffee Shop. There are currently 6 clerks performing each activity. Each activity has to be done to fulfill a customer order.

Activity

Description

Cycle Time (Seconds)

1

Greet the customer

15

2

Take the order

30

3

Brew the coffee

60

4

Grab the donut

40

5

Double check order for correctness

20

6

Pay / process credit card

30

a) Assume that each activity must occur in SEQUENCE (1, 2, … 6). Draw a capacity flow diagram, identity the bottleneck, what is the overall capacity?

b)

Dunk T. is the owner of this restaurant. Stephen, an ISE142 SJSU student, came into his shop and Dunk was impressed about Stephen’s ability to optimize processes. Based on Stephen’s quick analysis, he told Dunk that he could DOUBLE his capacity by adding one additional worker. Dunk was amazed and asked Stephen to join his team and prove the capacity could be doubled.

Confirm or discredit Stephen’s analysis. Can Dunk Donuts Shop capacity actually double by re-organizing & grouping tasks and adding one more worker? (Reminder: all steps must be in sequence)

Draw a capacity flow diagram and what is the new overall capacity.

 