A project manager is working on a project that will transform the organization’s operating model The project manager reviewed the budget location for vanous phases and was informed that upper management will not approve any additional funds Knowing that there are no additional funds available, how should the project manager proceed? Ensure that the budget is enough to cover the internal resources since external supplies can be covered by procurement Decide to work on the small deliveries leaving the big deliveres until the end of the proped and track crtical expenses Allocate the budget to the phases of the project and meet with upper management to consolidate the final funds Allocate the budget to the deliveries that have her business value for the organization than those with lower business value
 